Vanala 15 MW

The second of the power projects constructed by the company, with a project cost at 120.7 Crores (US$ 27m), six times that of Rajwakti, and an installed capacity of 15MW, almost four times that of Rajwakti, Vanala pushed the company to scale up its experience, operations, and manpower, and finally achieve the status and recognition as an infrastructure company of note within its field. Construction work on Vanala started in January 2007 with the project commissioned and operational by September 2009. Vanala has the operational capacity to generate 81.1 Million kWh of electricity per annum.

Infrastructure development (bridges, roads)

Infrastructure development work for Vanala Hydro-electric power project has now been completed. This includes bridges, roads and buildings for staff and construction material and various other structures, such as the foundations for the batching plant and the crushing plant.

Diversion Dam/Weir including feeder channel

The diversion dam on the river Nandakini is Barrage type and made of reinforced cement concrete with an under-sluice gate and side intake diverting water into a feeder channel of length 140 metres. The width of the structure is 38m, length 40 metres( five metres of which is below river water level)l with a height of 15 metres including foundation.

 

+ Enlarge

Silting Basin and Water conduit system

Silting basin

Measuring 115 m x 85m x 25 metres, the reinforced cement concrete silting basin reduces the speed of the flow of water resulting in the settlement of sediment and sand from river water. This process of removal greatly reduces the wear on the turbine blades with consequent reduction in operational and maintenance costs.

Water conduit system

i. Channel
The channel is a reinforced concrete box structure with dimensions of 1.9km length and internal dimensions of 3.2m x 2.2m with a wall thickness of 0.2 metre resting on a 0.4m thick bed. The discharge flow is 12.5 cumec.

ii. Fore-bay
The fore-bay is a 10m x w5.5m x h2.5m reinforced cement concrete water storage structure in the shape of a box at the end of the RCC water channel and the start of the mild steel water pipe.

iii. Pipe
The 2.6 kilometre long mild steel pipe with an internal diameter of 2.6 m and a wall thickness of eight millimetres is made up of individual 1.5 metre long hoop sections that are welded along the circumference to form one continuous pipe. The complete works were done in-house using a plate bending machine to bend mild steel plates which were then welded.

+ Enlarge 

iv. Penstock
A mild steel pipe of length 1.2 km with internal diameter 2.2m and wall thickness varying between 12-16 mm, further bifurcating into two 16 m long pipes of diameter, the penstock carries water under pressure to the turbines in the powerhouse.

Turbines and Powerhouse

The 42 m x 12 m x 11 m surface powerhouse houses two vertical Francis turbines of rated power of 7,500 kW each, set 10m below surface level, and a switchgear panel for synchronising the power generated with the local grid, and feeding it into the switchyard and transformer.

+ Enlarge 

Switchyard and Transmission

The generated power is stepped from 11kV to 66kV at 50 Hz through 20mVA transformer at the switchyard: works include the excavation of the foundation and the erection of the transformer and 25 transmission towers, stringing of 8 kilometres of double circuit “dog” conductor transmission line and finally site development.

 

+ Enlarge 

+ Enlarge 

© Copyright 2010, all rights reserved with Ramose Infra Private Limited site by: Cross Section